A reminder that as part of the Central Utility Plant Replacement (CUPR) Project contractors will be working in a number of buildings across campus to prepare for ventilation system upgrades.
Work will be done over the next few weeks in building mechanical rooms on the dates listed below during regular business hours:
- McKee Fisk (Mezzanine Mechanical Room): May 16 - 18
- South Gym (Basement and Mezzanine Mechanical rooms): May 19 - 21
- North Gym (Mechanical and Roof Mechanical rooms): May 24 - 25
- Grosse IT (Basement Pump and Mechanical rooms): May 26 - 28
Contact Facilities Management at 559.278.2373 if you have any questions. We appreciate your feedback on the CUPR project. Submit concerns here.
|