The sewer replacement project has modifications to the construction schedule. Please see attached revised schedule.
The main change is that the Barstow Avenue is taking longer than planned and the contractor is mobilizing more crews to make-up for this. We are moving the Grosse Industrial building sewer replacement earlier in the schedule. Some of the IT building restrooms could be temporarily closed. We will do everything possible to reduce the closure period.
If your building is not on the list, we anticipate no interruption to sewer service to your building. We will post signs on any restroom being closed with directions to closest available restroom.
- Viticulture/Enology Buildings affected 7-1 thru 7-20
- Joyal - Some restrooms temporarily shut-down 6-25 thru 7-9
- Grosse IT - Some restrooms temporarily shutdown 7-10 thru 7-12
- PHS - Restrooms temporarily shutdown 7-19 thru 7-27
- Social Science, Engineering West and North Gym - Some restrooms temporarily shutdown 7-9 thru 7-10
- Baker Hall - Some restrooms temporarily closed 7-31 thru 8-1
- McLane Hall - Some restrooms temporarily shutdown 8-8 thru 8-14
- Old Music - Some restrooms temporarily shutdown 8-15 thru 8-16
- Softball and Aquatics Center - Some restrooms temporarily shutdown 9-4 thru 9-5
If you have any questions or concerns, please call Facilities Planning at 278-4360.
|